Finishing a Revision to complete a Backup

Follow

Feature Availability: Version 9 or older

When you are backing up a Cubit Estimating job you may get a message like below. This is due to an unfinalised plan revision in the job.

job_export_plan_rev.png
Fig 1. Error Message

To be able to back up the job, you will first need to finish the revisions on the job.

You can do this by following these steps:

1. Open the Job.

2. Click the Plans tab.

Plans_Tab.png
Fig 2. Plans Tab

 

3. Click the Finish Revision button, in the Revisions section of the toolbar.

Finish_Button.pngFig 3. Finish Revision Button

You will now be able to back up the job normally.