Pro rata selected rates from the Estimating in Cubit Select

Follow

If you choose to Pro-rata from an estimate, the Total field will be shown. 

Follow the steps to apply a Pro-rata from the estimate for empty items only.

 

How to Pro-rata steps below.

1. Click Add Quote to insert a new quote for a Supplier.

mceclip0.png

Fig 1. Add Quote

 

2. Type the Supplier details then click Add button.

mceclip2.png

Fig 2. Supplier details

 

3. Select the Supplier and then click EXCL to mark all the items as excluded.

mceclip3.png

Fig 3. Exclude items

 

4. Delete rate for the items to be prorated from the estimate.

mceclip4.png

Fig 4. Delete Rate

 

5. Click Replace.

mceclip5.png

Fig 5. Replace

 

6. Type the new value into the Total box, to replace all empty items.

mceclip6.png

Fig 6.  Find Empty 

 

7. The total entered will be spread across the items as pro-rata from the estimate like below.

mceclip7.png

Fig 7: Pro-rata from Estimate 

 

8. For the leftover EXCL items, you can choose to fill the rate from the estimate.