Darren McFarlane commented, Sorry $65,00 /m2 that should read, not $65.50/m2
-
Darren McFarlane commented, Hi Michael, Yes i am aware that this function exists. The area that it draws from is the GFA you enter for the project, and therefore the costs per m2 is established, based on summation of costs un...
-
Darren McFarlane created a post, CompletedCost Planning - Element Unit Costs (Cubit)
When you create a cost plan in Global Estimating, after the items and costs have been developed in the trade breakup sheet, the provision exists for items to be tagged and at Job Summary Level, a c...
-
Darren McFarlane created a post, Cost Planning - Element Unit Costs (Cubit)
When you create a cost plan in Global Estimating, after the items and costs have been developed in the trade breakup sheet, the provision exists for items to be tagged and at Job Summary Level, a c...
-