Cubit Estimating: "Include in Trade"

Follow

Feature Availability: Cubit Estimating Standard, Professional, Professional + BIM module

The Include in Trade column in Cubit Estimating works similarly to Buildsoft's Global Estimating's 7 column mode's '+/- column'.

The Include in Trade can be used to calculate the Rate of a Trade Heading. When you tick the Include in Trade column, the item's Factor times Quantity is included in the Trade's Quantity column. The value in the Rate column of the Trade is then set to be the value in the Total divided by the value in the Quantity.

1. To add the Include in Trade column to your Item sheet, right-click the Name title bar in the Job List.

2. Select Column Chooser from the drop-down menu.

mceclip0.png
Fig 1. Column Chooser

3. From the Customisation menu double left mouse click Include in Trade to add it to your Job List.

mceclip1.png
Fig 2. Include in Trade Column

4. Click the X button on the top right of the Customisation menu to close the Customisation window

 

 