Changing Rounding for Items in Cubit Estimating

Follow

Rounding Quantities, Rates and Total allows us to make the number simpler but keeping its value close to what it was.

The Quantity, Rate, and Total columns can be set to the desired rounding option in Cubit Estimating --> Options from the Job manager window however this affects the items on the new jobs only.

To change the rounding option on existing job/items you need to modify the rounding value in the details window like below.

Select the item/s for which you want to change the rounding option. In the Details window and using the drop-down list set to one of the available rounding options for Quantity or Rate.

Note: Total rounding is available on Headings only.

mceclip0.png

Fig 1. Rounding on Details window